Hidden renovation costs — 14 lines that never appear in the quote

Hidden renovation costs — 14 lines that never appear in the quote

The quote said 84,000 PLN. The account showed 112,000 PLN. The gap was not a hidden contractor margin — it was fourteen lines nobody costed, because none of them is labour or a finishing material.

Problem

A contractor quote describes building work. A renovation is a great deal more than building work — and the rest comes out of the same wallet.

These lines share one trait: each looks trivial on its own. 900 PLN for a skip, 400 PLN for furniture storage, 1,200 PLN for an internal door you forgot about. Added up they usually come to 18-30% of the quoted value.

Here is the full list, ordered by how often each is missed.

Solution

Around the site

1. Debris removal and skip — 800-2,600 PLN. A 5 m³ skip in Warsaw is around 900 PLN, and a full flat renovation often needs two. Add carrying rubble down if there is no service lift.

2. Protecting the untouched part of the flat — 300-900 PLN. Sheeting, tape, floor protection boards in the hallway and stairwell.

3. Building management consent and deposit — 0-2,000 PLN. Many buildings charge a deposit for use of the lift and common stairs.

4. Power and water during the works — 200-700 PLN. More on a full renovation with drying and forced-air heating.

Around you

5. Temporary accommodation — 0-14,000 PLN. A full renovation means 2-3 months out of the flat. The single most under-counted line on this list.

6. Furniture storage — 300-1,800 PLN. Self-storage, 8-14 m³ for 2-3 months.

7. Transport and moving — 600-2,500 PLN, counting both directions.

Part of the renovation, absent from the quote

8. Internal doors with fitting — 900-2,600 PLN each. Across four rooms that is 4,000-10,000 PLN.

9. Lighting and electrical fittings — 2,000-9,000 PLN. Fixtures, sockets, switches, LED strips with drivers.

10. Sanitaryware and fittings — 3,000-25,000 PLN. Taps, WC, basin, shower or bath. Almost always outside a labour quote.

11. Curtain rails, blinds, insect screens — 800-4,500 PLN.

12. Post-renovation cleaning — 400-1,400 PLN. Construction dust needs three passes, not one.

After completion

13. Snagging and defects — 500-3,000 PLN. Even with a good crew, some defects only surface after a month of use.

14. Finishing after the crew — 1,000-5,000 PLN. Silicone, skirting, thresholds, door adjustment, touch-up paint.

What it comes to

For a 58 m² flat at standard finish against an 84,000 PLN quote, these lines realistically run 16,000-31,000 PLN. Even the lean version, with no temporary accommodation, comes to about 12,000 PLN.

Which is why a 15-20% contingency is not caution — it is simply the rest of the renovation, costed properly.

Checklist

  • Put the skip and debris removal in the budget — 800-2,600 PLN
  • Cost temporary accommodation for 2-3 months
  • Add furniture storage and transport both ways
  • Cost internal doors separately — 900-2,600 PLN each
  • Budget for sanitaryware, fittings and lighting
  • Check whether the building charges a deposit for lift and stairs
  • Set aside 400-1,400 PLN for post-renovation cleaning
  • Leave 1,000-5,000 PLN for snagging and finishing after the crew